When everyone purchases the gas boiler of their choice, a series of problems to be faced are the transportation of the boiler, installation to the factory, commissioning and subsequent normal operation. The tonnage of gas-fired boilers varies from 100 kg to more than 100 tons. We must pay more attention to the installation of the boiler. Don't cause problems in the later stage of the boiler because of the wrong installation method.
Song Gong, a technical engineer at Zhengzhou Fangkuai Boiler Plant, summarized some points that need to be paid attention to for boiler installation problems.
⑴. To determine the installation location, the boiler installation unit must have a boiler installation qualification certificate that meets the installation scope issued by the superior authority.
⑵, go through the registration procedures. According to the "Steam Boiler Safety Supervision Regulations", units using boilers should go through the registration procedures one by one. The boiler user unit should have a dedicated person responsible for boiler installation, responsible for getting in touch with the local boiler supervision agency, and filling out the installation notice.
When installing the boiler, a fireman must be involved, and a plumber, fitter, lifter, cold workman, electric welder and auxiliary workers are required.
⑶, organize staff to learn installation technical measures, safety technical measures, and be familiar with boiler drawings and related technical documents.
⑷. Before installing the boiler, check and accept the boiler body, combustion equipment, components, auxiliary machinery, and accessories according to the drawings, and make a record. If it is found that it does not meet the relevant standards, it should be submitted to the factory in time.
The installation process of gas boiler and auxiliary equipment is:
⑴, the boiler body, auxiliary equipment, accessory packaging boxes, and instrument packaging boxes should be hoisted according to the hoisting position specified by the manufacturer. The user shall be responsible for any damage to the hook during lifting.
⑵, the heavy-duty vehicle, lifting equipment, wire rope required for lashing, etc. must have sufficient load capacity, and should meet the technical specifications.
⑶. Before lifting, select lifting equipment according to the size and weight of large parts marked in the technical specifications, and formulate corresponding safety precautions.


Recently, Zhengzhou Fangkuai Boiler Sales Co., Ltd. traveled to Dhaka, the capital of Bangladesh, to attend the Bangladesh International Textile, Knitwear & Garment Industry Exhibition (BTKG 2026). It showcased industrial thermal equipment and system solutions adapted to the whole process of textile printing and dyeing, actively expanding the South Asian market.
Bangladesh is an important global producer and exporter of textiles and garments. As a pillar local industry, the textile sector has long-term and strong demand for high-efficiency, stable and energy-saving industrial boilers and thermal equipment, with broad market potential. This exhibition participation is an important measure for Zhengzhou Fangkuai Boiler Sales Co., Ltd. to advance its internationalization strategy and further explore overseas markets.

Relying on its technological accumulation and manufacturing advantages in the field of thermal energy equipment, the company provides targeted thermal energy solutions for local textile, printing and dyeing, garment manufacturing and other industries, helping enterprises improve production efficiency and reduce operating costs. In the future, Zhengzhou Fangkuai Boiler Sales Co., Ltd. will continue to focus on overseas market demands, continuously optimize its product and service system, facilitate the high-quality development of the global textile industry with professional and reliable products, and steadily enhance the brand’s competitiveness and influence in overseas markets.

Trust stems from quality
At the beginning of the new year, Fangkuai Boiler and a leading domestic new energy company have reached another important cooperation, successfully signing an order for a total of 500 steam tons.